Wednesday we poured the concrete, that was easy, the two lads (Gerry and Mikey), did the work and I erm....supervised and nodded approvingly from time to time. It was all over by lunch time and the concrete set by evening which meant that on Friday another Michael could arrive and start laying blocks and I could keep him supplied with blocks, cement and offers of tea.
So week one ended with the foundations poured and the sub-floor block work completed. We aren't quite out of the ground yet. I still need to fill the cavity in the block work with cement and sand then we can go on to complete the floor slab but fortunately we have had the worst weather over the past few days so I've achieved nothing. today is supposed to be a better day but I would point out that it is 4:58 am and I am writing this because the wind is howling so loudly outside that it is keeping me awake. we can only wait and see what the morning brings.